Page: 1
2
Question 1. Question
: (TCO 1) A project is defined
as a(n) _____ endeavor undertaken to create a(n) _____
product, service, or
result.
challenging; new
temporary; unique
new; challenging
ongoing; unique
Question 2. Question
: (TCO 1) Which document on a
project authorizes the project manager to begin work on the
project?
The scope
The schedule
The charter
The risk management plan
Question 3. Question
: (TCO 2) Project deliverables
are created in the _____ , which is completed during the
_____ phase of a
project.
charter; execution
scope; planning
schedule; planning
charter; planning
Week
2 Lecture
Comments:
Question 4. Question
: (TCO 2) Which statement is an
example of a project assumption?
“If the parts arrive late, we will not finish
on time.”
“We must get permits before we start work.”
“I believe the contracts will be signed by the
15th.”
“The paving of the parking lot will be
completed within this project.”
Week
2 Lecture
Comments:
Question 5. Question
: (TCO 3) The amount of time an
activity can be delayed without impacting the end date of the
project is known
as what?
Project risk
Slack
Critical path
Early start
Chapter
9
5
of 5
Comments:
Question 6. Question
: (TCO 3) What values are
calculated on the backward pass of a project network?
Early start; late start
Early start; early finish
Late start; late finish
Early finish; late finish
Chapter
9
Comments:
Question 7. Question
: (TCO 5) In which process of
risk management is the risk register initially created?
Plan risk management
Identify risks
Control risks
Qualitative risk analysis
Week
4 Lecture
5
of 5
Comments:
Question 8. Question
: (TCO 5) Contingency plans are
created
to proactively address the risk.
to respond to the risk should the risk occur.
to gather information on vital risks.
to avoid red risks in the project plan .
Week
4 Lecture
Comments:
Page: 1
2
Question 1. Question
: (TCO 1) Before one can begin
writing a charter, one must consider the most appropriate
organization for the
project. You are the project manager for a company that
integrates custom data
solutions for large corporate enterprises. This project will
span two or three
years and will cost tens of millions of dollars. This is a
large, very involved
project. Which of the five organization structures is most
suitable? Why?
Question 2. Question
: (TCO 2) You are a project
manager for a new hardware/software project. You just
received the project
charter and established your scope statement. Within the
scope statement, you
defined some of the key components to meet the overall
project objective.
Establishing requirements will be critical to define and get
approved. The
hardware will be new for your company, so you will need to
ensure the vendor is
selected and the hardware is appropriately installed into
your environment. The
supporting software will need to be designed and coded. It
will also need to be
installed and tested on the system. To ensure the users know
how to use the new
software, training will be needed for managers and the
associates. You have
assembled your team of experts and they are anxious to get
started.
Part 1: To ensure you have a clear scope for your team,
create a 2-level WBS. Don’t forget to include your WBS
numbering. (15 points)
Part 2: In your WBS, how many work packages have been
created? (5 points)
:
Question 3. Question
: (TCO 3) Compare and contrast
fast tracking and scope reduction as means of schedule
compression.
Question 4. Question
: (TCO 5) A firm hosts
data-mining servers and performs data mining for other
companies that do not
desire the costs of hardware, software, or expertise to data
mine their data.
The firm is planning to roll out faster data-mining software
that will reduce
the time to sift through customers’ data by a fraction of the
present time.
Part 1: List and discuss the major risk management functions
from a project management perspective for the data-mining
software project. (15
points)
Part 2: Describe a positive and negative risk event, the
consequences, and the risk-response plans for the data-mining
software project.
(15 points)
Question 5. Question
: (TCO 9) Compare and contrast
the development of a WBS in traditional project management
versus development
in an agile environment.
Page: 1
2
Question 1. Question
: (TCO 1) A project is defined
as a(n) _____ endeavor undertaken to create a(n) _____
product, service, or
result.
challenging; new
temporary; unique
new; challenging
ongoing; unique
Question 2. Question
: (TCO 1) Which document on a
project authorizes the project manager to begin work on the
project?
The scope
The schedule
The charter
The risk management plan
Question 3. Question
: (TCO 2) Project deliverables
are created in the _____ , which is completed during the
_____ phase of a
project.
charter; execution
scope; planning
schedule; planning
charter; planning
Week
2 Lecture
Comments:
Question 4. Question
: (TCO 2) Which statement is an
example of a project assumption?
“If the parts arrive late, we will not finish
on time.”
“We must get permits before we start work.”
“I believe the contracts will be signed by the
15th.”
“The paving of the parking lot will be
completed within this project.”
Week
2 Lecture
Comments:
Question 5. Question
: (TCO 3) The amount of time an
activity can be delayed without impacting the end date of the
project is known
as what?
Project risk
Slack
Critical path
Early start
Chapter
9
5
of 5
Comments:
Question 6. Question
: (TCO 3) What values are
calculated on the backward pass of a project network?
Early start; late start
Early start; early finish
Late start; late finish
Early finish; late finish
Chapter
9
Comments:
Question 7. Question
: (TCO 5) In which process of
risk management is the risk register initially created?
Plan risk management
Identify risks
Control risks
Qualitative risk analysis
Week
4 Lecture
5
of 5
Comments:
Question 8. Question
: (TCO 5) Contingency plans are
created
to proactively address the risk.
to respond to the risk should the risk occur.
to gather information on vital risks.
to avoid red risks in the project plan .
Week
4 Lecture
Comments:
Page: 1
2
Question 1. Question
: (TCO 1) Before one can begin
writing a charter, one must consider the most appropriate
organization for the
project. You are the project manager for a company that
integrates custom data
solutions for large corporate enterprises. This project will
span two or three
years and will cost tens of millions of dollars. This is a
large, very involved
project. Which of the five organization structures is most
suitable? Why?
Question 2. Question
: (TCO 2) You are a project
manager for a new hardware/software project. You just
received the project
charter and established your scope statement. Within the
scope statement, you
defined some of the key components to meet the overall
project objective.
Establishing requirements will be critical to define and get
approved. The
hardware will be new for your company, so you will need to
ensure the vendor is
selected and the hardware is appropriately installed into
your environment. The
supporting software will need to be designed and coded. It
will also need to be
installed and tested on the system. To ensure the users know
how to use the new
software, training will be needed for managers and the
associates. You have
assembled your team of experts and they are anxious to get
started.
Part 1: To ensure you have a clear scope for your team,
create a 2-level WBS. Don’t forget to include your WBS
numbering. (15 points)
Part 2: In your WBS, how many work packages have been
created? (5 points)
:
Question 3. Question
: (TCO 3) Compare and contrast
fast tracking and scope reduction as means of schedule
compression.
Question 4. Question
: (TCO 5) A firm hosts
data-mining servers and performs data mining for other
companies that do not
desire the costs of hardware, software, or expertise to data
mine their data.
The firm is planning to roll out faster data-mining software
that will reduce
the time to sift through customers’ data by a fraction of the
present time.
Part 1: List and discuss the major risk management functions
from a project management perspective for the data-mining
software project. (15
points)
Part 2: Describe a positive and negative risk event, the
consequences, and the risk-response plans for the data-mining
software project.
(15 points)
Question 5. Question
: (TCO 9) Compare and contrast
the development of a WBS in traditional project management
versus development
in an agile environment.
Page: 1
2
Question 1. Question
: (TCO 1) A project is defined
as a(n) _____ endeavor undertaken to create a(n) _____
product, service, or
result.
challenging; new
temporary; unique
new; challenging
ongoing; unique
Question 2. Question
: (TCO 1) Which document on a
project authorizes the project manager to begin work on the
project?
The scope
The schedule
The charter
The risk management plan
Question 3. Question
: (TCO 2) Project deliverables
are created in the _____ , which is completed during the
_____ phase of a
project.
charter; execution
scope; planning
schedule; planning
charter; planning
Week
2 Lecture
Comments:
Question 4. Question
: (TCO 2) Which statement is an
example of a project assumption?
“If the parts arrive late, we will not finish
on time.”
“We must get permits before we start work.”
“I believe the contracts will be signed by the
15th.”
“The paving of the parking lot will be
completed within this project.”
Week
2 Lecture
Comments:
Question 5. Question
: (TCO 3) The amount of time an
activity can be delayed without impacting the end date of the
project is known
as what?
Project risk
Slack
Critical path
Early start
Chapter
9
5
of 5
Comments:
Question 6. Question
: (TCO 3) What values are
calculated on the backward pass of a project network?
Early start; late start
Early start; early finish
Late start; late finish
Early finish; late finish
Chapter
9
Comments:
Question 7. Question
: (TCO 5) In which process of
risk management is the risk register initially created?
Plan risk management
Identify risks
Control risks
Qualitative risk analysis
Week
4 Lecture
5
of 5
Comments:
Question 8. Question
: (TCO 5) Contingency plans are
created
to proactively address the risk.
to respond to the risk should the risk occur.
to gather information on vital risks.
to avoid red risks in the project plan .
Week
4 Lecture
Comments:
Page: 1
2
Question 1. Question
: (TCO 1) Before one can begin
writing a charter, one must consider the most appropriate
organization for the
project. You are the project manager for a company that
integrates custom data
solutions for large corporate enterprises. This project will
span two or three
years and will cost tens of millions of dollars. This is a
large, very involved
project. Which of the five organization structures is most
suitable? Why?
Question 2. Question
: (TCO 2) You are a project
manager for a new hardware/software project. You just
received the project
charter and established your scope statement. Within the
scope statement, you
defined some of the key components to meet the overall
project objective.
Establishing requirements will be critical to define and get
approved. The
hardware will be new for your company, so you will need to
ensure the vendor is
selected and the hardware is appropriately installed into
your environment. The
supporting software will need to be designed and coded. It
will also need to be
installed and tested on the system. To ensure the users know
how to use the new
software, training will be needed for managers and the
associates. You have
assembled your team of experts and they are anxious to get
started.
Part 1: To ensure you have a clear scope for your team,
create a 2-level WBS. Don’t forget to include your WBS
numbering. (15 points)
Part 2: In your WBS, how many work packages have been
created? (5 points)
:
Question 3. Question
: (TCO 3) Compare and contrast
fast tracking and scope reduction as means of schedule
compression.
Question 4. Question
: (TCO 5) A firm hosts
data-mining servers and performs data mining for other
companies that do not
desire the costs of hardware, software, or expertise to data
mine their data.
The firm is planning to roll out faster data-mining software
that will reduce
the time to sift through customers’ data by a fraction of the
present time.
Part 1: List and discuss the major risk management functions
from a project management perspective for the data-mining
software project. (15
points)
Part 2: Describe a positive and negative risk event, the
consequences, and the risk-response plans for the data-mining
software project.
(15 points)
Question 5. Question
: (TCO 9) Compare and contrast
the development of a WBS in traditional project management
versus development
in an agile environment.
Page: 1
2
Question 1. Question
: (TCO 1) A project is defined
as a(n) _____ endeavor undertaken to create a(n) _____
product, service, or
result.
challenging; new
temporary; unique
new; challenging
ongoing; unique
Question 2. Question
: (TCO 1) Which document on a
project authorizes the project manager to begin work on the
project?
The scope
The schedule
The charter
The risk management plan
Question 3. Question
: (TCO 2) Project deliverables
are created in the _____ , which is completed during the
_____ phase of a
project.
charter; execution
scope; planning
schedule; planning
charter; planning
Week
2 Lecture
Comments:
Question 4. Question
: (TCO 2) Which statement is an
example of a project assumption?
“If the parts arrive late, we will not finish
on time.”
“We must get permits before we start work.”
“I believe the contracts will be signed by the
15th.”
“The paving of the parking lot will be
completed within this project.”
Week
2 Lecture
Comments:
Question 5. Question
: (TCO 3) The amount of time an
activity can be delayed without impacting the end date of the
project is known
as what?
Project risk
Slack
Critical path
Early start
Chapter
9
5
of 5
Comments:
Question 6. Question
: (TCO 3) What values are
calculated on the backward pass of a project network?
Early start; late start
Early start; early finish
Late start; late finish
Early finish; late finish
Chapter
9
Comments:
Question 7. Question
: (TCO 5) In which process of
risk management is the risk register initially created?
Plan risk management
Identify risks
Control risks
Qualitative risk analysis
Week
4 Lecture
5
of 5
Comments:
Question 8. Question
: (TCO 5) Contingency plans are
created
to proactively address the risk.
to respond to the risk should the risk occur.
to gather information on vital risks.
to avoid red risks in the project plan .
Week
4 Lecture
Comments:
Page: 1
2
Question 1. Question
: (TCO 1) Before one can begin
writing a charter, one must consider the most appropriate
organization for the
project. You are the project manager for a company that
integrates custom data
solutions for large corporate enterprises. This project will
span two or three
years and will cost tens of millions of dollars. This is a
large, very involved
project. Which of the five organization structures is most
suitable? Why?
Question 2. Question
: (TCO 2) You are a project
manager for a new hardware/software project. You just
received the project
charter and established your scope statement. Within the
scope statement, you
defined some of the key components to meet the overall
project objective.
Establishing requirements will be critical to define and get
approved. The
hardware will be new for your company, so you will need to
ensure the vendor is
selected and the hardware is appropriately installed into
your environment. The
supporting software will need to be designed and coded. It
will also need to be
installed and tested on the system. To ensure the users know
how to use the new
software, training will be needed for managers and the
associates. You have
assembled your team of experts and they are anxious to get
started.
Part 1: To ensure you have a clear scope for your team,
create a 2-level WBS. Don’t forget to include your WBS
numbering. (15 points)
Part 2: In your WBS, how many work packages have been
created? (5 points)
:
Question 3. Question
: (TCO 3) Compare and contrast
fast tracking and scope reduction as means of schedule
compression.
Question 4. Question
: (TCO 5) A firm hosts
data-mining servers and performs data mining for other
companies that do not
desire the costs of hardware, software, or expertise to data
mine their data.
The firm is planning to roll out faster data-mining software
that will reduce
the time to sift through customers’ data by a fraction of the
present time.
Part 1: List and discuss the major risk management functions
from a project management perspective for the data-mining
software project. (15
points)
Part 2: Describe a positive and negative risk event, the
consequences, and the risk-response plans for the data-mining
software project.
(15 points)
Question 5. Question
: (TCO 9) Compare and contrast
the development of a WBS in traditional project management
versus development
in an agile environment.